PROJECT

DOMINATOR 2023

Title : Dominator

Year : 2023

What : Special rigging solutions

Information about.

For Dominator 2023, we handled the lifting operations of the central object. The stage element, with a total mass of 13,000 kg, a width of 29 meters, and a height of 27 meters, was placed against the stage structure from the ground using two cranes. The construction utilized FD34, FD44, ST, and TT trusses. To lift the object as a whole, we developed a web of steel cables and pulleys to evenly distribute the weight and lift the object safely and systematically. It’s serious business, but we’re more than capable of handling it.

Facts:

– Lifting plan and execution

– 12,700kg lift

For more information, please contact us.